3D design service:
Here you can see the result of a recent project: below rendering and actual result.
Below a movie showing the process of this installation.
It took our dealer 6 days with 2 persons to install this cinema.
day 1: install speakers
day 2: install wall fabric stretch profiles, acoustic foam and LED profiles
day 3: installation fabric
day 4: finishing fabric walls, installation screen and electronics
day 5: carpet installation
day 6: placement seats and audio calibration
We supplied our dealer with the following:
Matiz Seats
carpet
acoustic foam
wall fabric and tension profiles
LED profiles and covers to match with our tension profiles